United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Oklahoma (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3342 MW
Active in queue3,854 MW27 requests
Agreement signed3,834 MW26 requests
Withdrawn4010.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2017-027, Carter County
Onshore wind
140 MWOperating Carter, OKSPP May 20172021
Onshore wind project GEN-2017-047, Beaver County
Onshore wind
102 MWOperating Beaver, OKSPP May 20172024
Solar project GEN-2017-036, Kiowa County
Solar
100 MWOperating Kiowa, OKSPP May 20172025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)