United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Oklahoma (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown71,128 MW
Active in queue1,936 MW12 requests
Agreement signed1,128 MW7 requests
Withdrawn243,494 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2021-053, Muskogee County
Solar
300 MWAgreement signed Muskogee, OKSPP Apr 2021target 2031
Solar project GEN-2021-047, Mayes County
Solar
250 MWAgreement signed Mayes, OKSPP Apr 2021target 2029
Solar project GEN-2021-018, Noble County
Solar
231 MWAgreement signed Noble, OKSPP Apr 2021target 2028
Battery storage project GEN-2021-041, Canadian County
Battery storage
100 MWAgreement signed Canadian, OKSPP Apr 2021target 2027
Onshore wind project GI-96, Lincoln County
Onshore wind
97.5 MWAgreement signed Lincoln, OKSoutheast Oct 2021target 2026
Battery storage project GEN-2021-052, Muskogee County
Battery storage
75.0 MWAgreement signed Muskogee, OKSPP Apr 2021target 2031
Battery storage project GEN-2021-019, Noble County
Battery storage
74.9 MWAgreement signed Noble, OKSPP Apr 2021target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)