Interconnection queue in Ohio (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6228 MW
Active in queue228 MW6 requests
Agreement signed0.0 MW0 requests
Withdrawn13811.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AH2-010, Logan County
Solar
100 MWIn study Logan, OHPJM Oct 2021target 2024
Solar + storage project AH2-028, Pickaway County
Solar + storage
44.0 MWIn study Pickaway, OHPJM Nov 2021target 2025
Solar project AH2-009, Morrow County
Solar
40.0 MWIn study Morrow, OHPJM Oct 2021target 2024
Solar project AH2-028A, Pickaway County
Solar
20.0 MWIn study Pickaway, OHPJM Nov 2021target 2025
Other project AH2-006, Pickaway County
Other
14.2 MWIn study Pickaway, OHPJM Oct 2021target 2024
Other project AH2-007, Fayette County
Other
10.1 MWIn study Fayette, OHPJM Oct 2021target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)