United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in North Dakota (2012 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3678 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn3678 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project MPC02600, Mclean County
Onshore wind
400 MWWithdrawn / abandoned Mclean, NDMISO Dec 2012target 2016
Onshore wind project GI-1211, Williams County
Onshore wind
250 MWWithdrawn / abandoned Williams, NDWest Aug 2012target 2014
Onshore wind project J251, Ramsey County
Onshore wind
27.5 MWWithdrawn / abandoned Ramsey, NDMISO Sep 2012

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)