United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in North Dakota (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3425 MW
Active in queue383 MW1 requests
Agreement signed0.0 MW0 requests
Withdrawn62,201 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-1410, Williams County
Onshore wind Β· Lindahl Wind
150 MWOperating Williams, NDWest Jun 2014target 2014
Onshore wind project GI-1414, Stark County
Onshore wind Β· Brady Wind
150 MWOperating Stark, NDWest Oct 2014target 2015
Gas project GI-1406, Williams County
Gas Β· Basin Electric
125 MWOperating Williams, NDWest Jun 2014target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)