United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in North Dakota (2013 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5601 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn5872 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J290, Rolette County
Onshore wind
150 MWOperating Rolette, NDMISO Aug 20132014
Onshore wind project J316, Dickey County
Onshore wind
150 MWOperating Dickey, NDMISO Nov 20132016
Onshore wind project J302, Emmons County
Onshore wind
101 MWOperating Emmons, NDMISO Nov 20132019
Onshore wind project J262, Stutsman County
Onshore wind
100 MWOperating Stutsman, NDMISO Jan 20132014
Onshore wind project J263, Stutsman County
Onshore wind
100 MWOperating Stutsman, NDMISO Jan 20132014

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)