Completed queue projects in North Carolina (2012 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4140 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn103,274 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 4910, Duplin County
Solar Β· Duke Energy Progress, LLC
64.8 MWOperating Duplin, NCSoutheast Apr 20122015
Gas project 25667, Richmond County
Gas Β· Duke Energy Progress, LLC
32.0 MWOperating Richmond, NCSoutheast Jan 20122012
Solar project 4904, Bladen County
Solar Β· Tangent Energy Solutions, INC.
23.0 MWOperating Bladen, NCSoutheast Aug 20122015
Morgan's Corner Solar
Solar
20.0 MWOperating Pasquotank, NCPJM Apr 20122015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)