Completed queue projects in New Mexico (2013 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown563.0 MW
Active in queue42.3 MW1 requests
Agreement signed42.3 MW1 requests
Withdrawn81,704 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2013-022, Quay County
Solar
25.0 MWOperating Quay, NMSPP Sep 20132016
Solar project SGI-PNM-2013-04, Bernalillo County
Solar
10.0 MWOperating Bernalillo, NMWest Aug 2013
NMRD Data Center LLC
Solar
10.0 MWOperating Bernalillo, NMWest Nov 2013
Solar project SGI-PNM-2013-02, Valencia County
Solar
9.0 MWOperating Valencia, NMWest May 2013
Solar project SGI-PNM-2013-03, Sandoval County
Solar
9.0 MWOperating Sandoval, NMWest May 2013

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)