πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in New Jersey (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown51,419 MW
Active in queue1,419 MW5 requests
Agreement signed21.6 MW2 requests
Withdrawn427,050 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Ocean Wind
Offshore wind
816 MWPaused / redesign Ocean, NJPJM May 2018target 2026
Ocean Wind LLC
Offshore wind
432 MWPaused / redesign Cape May, NJPJM Sep 2018target 2026
Pilesgrove Solar Project
Solar
149 MWPaused / redesign Salem, NJPJM Sep 2018target 2027
Warren Glen Storage
Battery storage
20.0 MWAgreement signed Warren, NJPJM Sep 2018target 2024
Monroe-Sicklerville Road LF Solar
Solar
1.6 MWAgreement signed Gloucester, NJPJM Mar 2018target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)