United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in New Jersey (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown106,761 MW
Active in queue7,831 MW19 requests
Agreement signed0.0 MW0 requests
Withdrawn106,761 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project AH2-196, Monmouth County
Onshore wind
1,600 MWWithdrawn / abandoned Monmouth, NJPJM Mar 2022target 2031
Offshore wind project AI1-046, Monmouth County
Offshore wind
1,600 MWWithdrawn / abandoned Monmouth, NJPJM May 2022target 2031
Offshore wind project AH2-240, Monmouth County
Offshore wind
1,493 MWWithdrawn / abandoned Monmouth, NJPJM Mar 2022target 2027
Onshore wind project AH2-285, Middlesex County
Onshore wind
1,400 MWWithdrawn / abandoned Middlesex, NJPJM Mar 2022target 2029
Onshore wind project AH2-287, Monmouth County
Onshore wind
600 MWWithdrawn / abandoned Monmouth, NJPJM Mar 2022target 2029
Solar + storage project AH2-293, Warren County
Solar + storage
50.0 MWWithdrawn / abandoned Warren, NJPJM Mar 2022target 2025
Solar + storage project AH2-201, Cumberland County
Solar + storage
5.0 MWWithdrawn / abandoned Cumberland, NJPJM Mar 2022target 2025
Solar + storage project AH2-202, Hunterdon County
Solar + storage
5.0 MWWithdrawn / abandoned Hunterdon, NJPJM Mar 2022target 2025
Solar + storage project AH2-254, Mercer County
Solar + storage
5.0 MWWithdrawn / abandoned Mercer, NJPJM Mar 2022target 2025
Solar + storage project AH2-200
Solar + storage
3.0 MWWithdrawn / abandoned NJPJM Mar 2022target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)