United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in New Jersey (2012 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown223,823 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn223,823 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

22 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project Y2-013, Union County
Gas
800 MWWithdrawn / abandoned Union, NJPJM May 2012target 2017
Gas project Y1-025, Middlesex County
Gas
785 MWWithdrawn / abandoned Middlesex, NJPJM Feb 2012target 2015
Gas project Y3-001, Hudson County
Gas
705 MWWithdrawn / abandoned Hudson, NJPJM Nov 2012target 2017
Gas project Y1-011, Middlesex County
Gas
520 MWWithdrawn / abandoned Middlesex, NJPJM Feb 2012target 2016
B.L. England Station
Gas
452 MWWithdrawn / abandoned Cape May, NJPJM Feb 2012target 2021
Gas project Y2-083, Essex County
Gas
218 MWWithdrawn / abandoned Essex, NJPJM Oct 2012target 2016
Gas project Y2-102, Salem County
Gas
193 MWWithdrawn / abandoned Salem, NJPJM Nov 2012target 2016
Gas project Y2-110, Cape May County
Gas
40.0 MWWithdrawn / abandoned Cape May, NJPJM Nov 2012target 2016
Cape May Energy Center (CMEC)
Gas
34.0 MWWithdrawn / abandoned Cape May, NJPJM Apr 2012target 2021
Gas project Y1-076, Cape May County
Gas
18.1 MWWithdrawn / abandoned Cape May, NJPJM Apr 2012target 2015
Solar project Y1-017, Burlington County
Solar
10.0 MWWithdrawn / abandoned Burlington, NJPJM Feb 2012target 2013
Solar project Y1-046, Monmouth County
Solar
8.0 MWWithdrawn / abandoned Monmouth, NJPJM Mar 2012target 2013
Allerton Road Solar Farm
Solar
8.0 MWWithdrawn / abandoned Hunterdon, NJPJM Jan 2012target 2015
Solar project Y1-037
Solar
6.0 MWWithdrawn / abandoned NJPJM Mar 2012
Solar project Y1-055, Ocean County
Solar
5.0 MWWithdrawn / abandoned Ocean, NJPJM Apr 2012target 2015
Solar project Y1-038, Sussex County
Solar
5.0 MWWithdrawn / abandoned Sussex, NJPJM Mar 2012target 2013
Solar project X4-047, Warren County
Solar
4.0 MWWithdrawn / abandoned Warren, NJPJM Jan 2012target 2013
Solar project Y1-009, Mercer County
Solar
4.0 MWWithdrawn / abandoned Mercer, NJPJM Feb 2012target 2012
Solar project Y1-042, Cumberland County
Solar
3.5 MWWithdrawn / abandoned Cumberland, NJPJM Mar 2012target 2014
Fredon Solar Farm
Solar
2.0 MWWithdrawn / abandoned Sussex, NJPJM Apr 2012target 2015
Other project Y1-010, Salem County
Other
1.9 MWWithdrawn / abandoned Salem, NJPJM Feb 2012target 2012
Solar project Y2-029, Atlantic County
Solar
0.4 MWWithdrawn / abandoned Atlantic, NJPJM Jun 2012

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)