Gas project Y1-076, Cape May County

Gas project Y1-076, Cape May County is a 18.1 MW gas request withdrawn in the PJM interconnection queue, in Cape May County, New Jersey, connecting to AEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2012 (completed)
  2. Withdrawn / abandonedMay 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Y1-076
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEC
Connection point (POI)
BL England 138kV
Location
Cape May County, New Jersey
Technology
Gas: 18.1 MW
Total requested
18.1 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
30 April 2012
Proposed online date
June 2015
Withdrawn
May 2012

Location

Marker shows the centre of Cape May County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Cape May County