United States β€Ί Grid β€Ί Interconnection queues β€Ί New Hampshire

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in New Hampshire (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown10198 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn10198 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar
Solar
30.0 MWWithdrawn / abandoned Cheshire, NHISO-NE Mar 2017target 2018
Solar
Solar
20.0 MWWithdrawn / abandoned Grafton, NHISO-NE Aug 2017target 2019
Solar
Solar
20.0 MWWithdrawn / abandoned Coos, NHISO-NE Oct 2017target 2022
Solar
Solar
20.0 MWWithdrawn / abandoned Grafton, NHISO-NE Oct 2017target 2020
Solar
Solar
20.0 MWWithdrawn / abandoned Grafton, NHISO-NE Aug 2017target 2022
Claremont Solar
Solar
20.0 MWWithdrawn / abandoned Sullivan, NHISO-NE Aug 2017target 2023
Solar
Solar
20.0 MWWithdrawn / abandoned Grafton, NHISO-NE Oct 2017target 2020
Solar
Solar
20.0 MWWithdrawn / abandoned Hillsborough, NHISO-NE Aug 2017target 2022
Solar
Solar
20.0 MWWithdrawn / abandoned Grafton, NHISO-NE Aug 2017target 2019
CHP
Gas
8.0 MWWithdrawn / abandoned Coos, NHISO-NE Apr 2017target 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)