Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown183,850 MW
Active in queue17.6 GW51 requests
Agreement signed8,552 MW25 requests
Withdrawn183,850 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

18 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Alum Geothermal
Geothermal
530 MWWithdrawn / abandoned Esmeralda, NVCAISO Apr 2021target 2025
Solar + storage project Company MF, Humboldt County
Solar + storage
500 MWWithdrawn / abandoned Humboldt, NVWest Sep 2021target 2024
Battery storage project Company 199, Clark County
Battery storage
300 MWWithdrawn / abandoned Clark, NVWest Sep 2021target 2025
Solar + storage project Company LQ, Washoe County
Solar + storage
300 MWWithdrawn / abandoned Washoe, NVWest Sep 2021target 2024
Wind + storage project Company LH, White Pine County
Wind + storage
200 MWWithdrawn / abandoned White Pine, NVWest Mar 2021target 2025
Solar + storage project Company LJ, White Pine County
Solar + storage
200 MWWithdrawn / abandoned White Pine, NVWest Mar 2021target 2025
Battery storage project Company LI, Churchill County
Battery storage
200 MWWithdrawn / abandoned Churchill, NVWest Mar 2021target 2024
Solar + storage project Company MD, Lyon County
Solar + storage
200 MWWithdrawn / abandoned Lyon, NVWest Sep 2021target 2026
Solar + storage project Company MC, Lyon County
Solar + storage
200 MWWithdrawn / abandoned Lyon, NVWest Sep 2021target 2026
Battery storage project Company 203, Clark County
Battery storage
200 MWWithdrawn / abandoned Clark, NVWest Sep 2021target 2029
Battery storage project Company 198, Clark County
Battery storage
200 MWWithdrawn / abandoned Clark, NVWest Mar 2021target 2024
Pearl Geothermal
Geothermal
200 MWWithdrawn / abandoned Esmeralda, NVCAISO Apr 2021target 2027
Solar + storage project Company 196, Clark County
Solar + storage
200 MWWithdrawn / abandoned Clark, NVWest Mar 2021target 2024
Onshore wind project Company LS, Lyon County
Onshore wind
180 MWWithdrawn / abandoned Lyon, NVWest Sep 2021target 2024
Battery storage project Company 205, Clark County
Battery storage
100 MWWithdrawn / abandoned Clark, NVWest Sep 2021target 2024
Solar + storage project Company LA, Storey County
Solar + storage
100 MWWithdrawn / abandoned Storey, NVWest Mar 2021target 2022
Geothermal project Company LO, Pershing County
Geothermal
20.0 MWWithdrawn / abandoned Pershing, NVWest Sep 2021target 2025
Geothermal project Company LN, Esmeralda County
Geothermal
19.8 MWWithdrawn / abandoned Esmeralda, NVWest Apr 2021target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)