Withdrawn queue requests in Nevada (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown92,351 MW
Active in queue5,365 MW17 requests
Agreement signed3,490 MW13 requests
Withdrawn92,351 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project Company KS, White Pine County
Onshore wind
575 MWWithdrawn / abandoned White Pine, NVWest Sep 2020target 2024
Bonanza Solar 2
Solar + storage
450 MWWithdrawn / abandoned Clark, NVCAISO Apr 2020target 2024
Solar + storage project Company KQ, Pershing County
Solar + storage
360 MWWithdrawn / abandoned Pershing, NVWest Sep 2020target 2026
Solar + storage project Company KV, Storey County
Solar + storage
250 MWWithdrawn / abandoned Storey, NVWest Sep 2020target 2022
Solar + storage project Company KP, Pershing County
Solar + storage
250 MWWithdrawn / abandoned Pershing, NVWest Sep 2020target 2023
Solar project Company KX, White Pine County
Solar
175 MWWithdrawn / abandoned White Pine, NVWest Sep 2020target 2028
Battery storage project Company 190, Clark County
Battery storage
100 MWWithdrawn / abandoned Clark, NVWest Feb 2020target 2023
Solar + storage project Company KM, Nye County
Solar + storage
100 MWWithdrawn / abandoned Nye, NVWest Mar 2020target 2023
Solar + storage project Company KT, Lander County
Solar + storage
91.0 MWWithdrawn / abandoned Lander, NVWest Sep 2020target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)