United States β€Ί Grid β€Ί Interconnection queues β€Ί Nebraska

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Nebraska (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown91,690 MW
Active in queue1,690 MW9 requests
Agreement signed1,380 MW8 requests
Withdrawn111,840 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2017-210, Cedar County
Solar
310 MWPaused / redesign Cedar, NESPP Nov 2017target 2026
Onshore wind project BHBE G13, Custer County
Onshore wind
300 MWAgreement signed Custer, NEWest Jul 2017target 2023
Onshore wind project GEN-2017-181, Lancaster County
Onshore wind
300 MWAgreement signed Lancaster, NESPP Nov 2017target 2028
Onshore wind project GEN-2017-201, Wayne County
Onshore wind
250 MWAgreement signed Wayne, NESPP Nov 2017target 2028
Onshore wind project GEN-2017-144, Holt County
Onshore wind
200 MWAgreement signed Holt, NESPP Nov 2017target 2028
Onshore wind project GEN-2017-182, Lancaster County
Onshore wind
128 MWAgreement signed Lancaster, NESPP Nov 2017target 2028
Onshore wind project GEN-2017-234, Greeley County
Onshore wind
115 MWAgreement signed Greeley, NESPP Nov 20172024
Onshore wind project GEN-2017-105, Burt County
Onshore wind
75.0 MWAgreement signed Burt, NESPP Jul 2017target 2026
Battery storage project GEN-2017-198, Douglas County
Battery storage
11.6 MWAgreement signed Douglas, NESPP Nov 2017target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)