Solar interconnection queue in Montana

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3602 MW
Active in queue602 MW3 requests
Agreement signed0.0 MW0 requests
Withdrawn1373,213 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 405, Rosebud County
Solar
300 MWPaused / redesign Rosebud, MTWest Feb 2021target 2024
Solar project 419, Big Horn County
Solar
300 MWIn study Big Horn, MTWest Feb 2022target 2025
Solar project 454, Gallatin County
Solar
2.0 MWIn study Gallatin, MTWest Dec 2023target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)