United States β€Ί Grid β€Ί Interconnection queues β€Ί Montana

OCTARY USA Β· INTERCONNECTION QUEUES

Other interconnection queue in Montana

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2502 MW
Active in queue502 MW2 requests
Agreement signed0.0 MW0 requests
Withdrawn237.0 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Other project 390, Yellowstone County
Other
500 MWIn study Yellowstone, MTWest Aug 2020target 2023
Other project G0710, Flathead County
Other
1.6 MWIn study Flathead, MTWest Nov 2021target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)