United States β€Ί Grid β€Ί Interconnection queues β€Ί Mississippi

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Mississippi (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown81,045 MW
Active in queue1,045 MW8 requests
Agreement signed995 MW7 requests
Withdrawn273,788 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 423, Clay County
Solar
200 MWAgreement signed Clay, MSSoutheast Apr 2020target 2026
Battery storage project 429, Clay County
Battery storage
200 MWAgreement signed Clay, MSSoutheast Apr 2020target 2028
Solar project 425, Chickasaw County
Solar
150 MWAgreement signed Chickasaw, MSSoutheast Apr 2020target 2027
Solar project J1672, Hinds County
Solar
150 MWAgreement signed Hinds, MSMISO Jun 2020target 2025
Solar project 422, Chickasaw County
Solar
145 MWAgreement signed Chickasaw, MSSoutheast Apr 2020target 2027
Solar project J1748, Desoto County
Solar
100 MWAgreement signed Desoto, MSMISO Jul 2020target 2025
Battery storage project 424, Clay County
Battery storage
50.0 MWAgreement signed Clay, MSSoutheast Apr 2020target 2026
Solar project J1747, Madison County
Solar
50.0 MWUnder construction Madison, MSMISO Jun 2020target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)