United States β€Ί Grid β€Ί Interconnection queues β€Ί Mississippi

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Mississippi (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8882 MW
Active in queue512 MW5 requests
Agreement signed212 MW3 requests
Withdrawn8882 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J945, Washington County
Solar
200 MWWithdrawn / abandoned Washington, MSMISO Jun 2017target 2019
Solar project 325, Lowndes County
Solar
150 MWWithdrawn / abandoned Lowndes, MSSoutheast Aug 2017
Solar project J910, Hinds County
Solar
150 MWWithdrawn / abandoned Hinds, MSMISO Jun 2017target 2020
Solar project 307, Lowndes County
Solar
100 MWWithdrawn / abandoned Lowndes, MSSoutheast Jan 2017
Solar project IC-576, Clarke County
Solar
80.0 MWWithdrawn / abandoned Clarke, MSSoutheast Jan 2017
Solar project 334, Quitman County
Solar
71.0 MWWithdrawn / abandoned Quitman, MSSoutheast Oct 2017
Solar project 315, Monroe County
Solar
66.0 MWWithdrawn / abandoned Monroe, MSSoutheast May 2017
Solar project 316, Monroe County
Solar
65.0 MWWithdrawn / abandoned Monroe, MSSoutheast May 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)