United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Minnesota (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5500 MW
Active in queue500 MW5 requests
Agreement signed80.0 MW1 requests
Withdrawn273,827 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J967, Mower County
Onshore wind
150 MWUnder construction Mower, MNMISO Mar 2018target 2023
Solar project J1072, Mower County
Solar
150 MWUnder construction Mower, MNMISO Mar 2018target 2023
Solar project J1124, Olmsted County
Solar
100 MWUnder construction Olmsted, MNMISO Mar 2018target 2024
Solar project J1164, Rock County
Solar
80.0 MWAgreement signed Rock, MNMISO Mar 2018target 2024
Battery storage project J1045, Murray County
Battery storage
20.0 MWUnder construction Murray, MNMISO Mar 2018target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)