United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Minnesota (2011 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project G959, Goodhue County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project G991, Fillmore County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project G961, Goodhue County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project G960, Goodhue County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J198, Lyon County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project J193, Otter Tail County Onshore wind |
50.0 MW | Withdrawn / abandoned |
| Onshore wind project J223, Mower County Onshore wind |
30.0 MW | Withdrawn / abandoned |
| Onshore wind project J216, Mower County Onshore wind |
25.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)