Completed queue projects in Minnesota (2013 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4351 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn11915 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J278, Mower County
Onshore wind
200 MWOperating Mower, MNMISO Mar 20132014
Gas project J299, Blue Earth County
Gas
73.0 MWOperating Blue Earth, MNMISO Nov 20132018
Onshore wind project H071, Stearns County
Onshore wind
40.0 MWOperating Stearns, MNMISO Jan 20132011
Onshore wind project G858, Stearns County
Onshore wind
38.0 MWOperating Stearns, MNMISO Jan 20132009

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)