United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Michigan (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4564 MW
Active in queue564 MW4 requests
Agreement signed100 MW1 requests
Withdrawn245,303 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J799, Washtenaw County
Solar
189 MWUnder construction Washtenaw, MIMISO Jun 2017target 2021
Solar project J875, Lenawee County
Solar
150 MWUnder construction Lenawee, MIMISO Jun 2017target 2022
Solar project J857, Calhoun County
Solar
125 MWUnder construction Calhoun, MIMISO Jun 2017target 2022
Southwest Michigan Energy Center
Solar
100 MWAgreement signed Van Buren, MIPJM Dec 2017target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)