United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Michigan (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown101,739 MW
Active in queue30.0 MW1 requests
Agreement signed30.0 MW1 requests
Withdrawn101,739 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J451, Oakland County
Gas
500 MWWithdrawn / abandoned Oakland, MIMISO May 2015target 2018
Gas project J444, Wayne County
Gas
235 MWWithdrawn / abandoned Wayne, MIMISO May 2015target 2017
Onshore wind project J537, Sanilac County
Onshore wind
200 MWWithdrawn / abandoned Sanilac, MIMISO Nov 2015target 2017
Onshore wind project J450, Huron County
Onshore wind
200 MWWithdrawn / abandoned Huron, MIMISO May 2015target 2016
Onshore wind project J496, Sanilac County
Onshore wind
152 MWWithdrawn / abandoned Sanilac, MIMISO Nov 2015target 2017
Onshore wind project J470, Marquette County
Onshore wind
150 MWWithdrawn / abandoned Marquette, MIMISO Jul 2015target 2018
Onshore wind project J452, Sanilac County
Onshore wind
150 MWWithdrawn / abandoned Sanilac, MIMISO May 2015
Onshore wind project J521, Huron County
Onshore wind
100 MWWithdrawn / abandoned Huron, MIMISO Nov 2015target 2017
Solar project J471, Wayne County
Solar
50.0 MWWithdrawn / abandoned Wayne, MIMISO Aug 2015target 2016
Battery storage project J445, Gratiot County
Battery storage
2.0 MWWithdrawn / abandoned Gratiot, MIMISO May 2015target 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)