United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Michigan (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3493 MW
Active in queue3,078 MW24 requests
Agreement signed1,568 MW14 requests
Withdrawn293,737 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J1194, Midland County
Onshore wind
225 MWOperating Midland, MIMISO Apr 20192021
Solar project J1401, Branch County
Solar
150 MWOperating Branch, MIMISO Apr 20192024
Onshore wind project J1319, Huron County
Onshore wind
118 MWOperating Huron, MIMISO Apr 20192022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)