Gas project X3-102, Charles County Gas |
971 MW | Withdrawn / abandoned |
Charles, MD | PJM |
Oct 2011 | target 2016 |
Gas project X3-103, Charles County Gas |
971 MW | Withdrawn / abandoned |
Charles, MD | PJM |
Oct 2011 | target 2016 |
Mattawoman Energy Gas |
894 MW | Withdrawn / abandoned |
Prince George's, MD | PJM |
Oct 2011 | target 2022 |
Gas project X2-030, Charles County Gas |
830 MW | Withdrawn / abandoned |
Charles, MD | PJM |
May 2011 | target 2016 |
Gas project X4-026, Prince George's County Gas |
792 MW | Withdrawn / abandoned |
Prince George's, MD | PJM |
Nov 2011 | target 2015 |
Gas project W4-044, Charles County Gas |
725 MW | Withdrawn / abandoned |
Charles, MD | PJM |
Jan 2011 | target 2015 |
Gas project X3-088, Montgomery County Gas |
440 MW | Withdrawn / abandoned |
Montgomery, MD | PJM |
Oct 2011 | target 2016 |
Great Bay Wind Farm Onshore wind |
150 MW | Withdrawn / abandoned |
Somerset, MD | PJM |
Apr 2011 | target 2018 |
Gas project X4-007, Charles County Gas |
60.0 MW | Withdrawn / abandoned |
Charles, MD | PJM |
Nov 2011 | target 2015 |
Solar project X3-009, Dorchester County Solar |
20.0 MW | Withdrawn / abandoned |
Dorchester, MD | PJM |
Aug 2011 | target 2017 |
Solar project X2-045, Worcester County Solar |
20.0 MW | Withdrawn / abandoned |
Worcester, MD | PJM |
Jun 2011 | target 2013 |
Solar project X1-029, Dorchester County Solar |
20.0 MW | Withdrawn / abandoned |
Dorchester, MD | PJM |
Mar 2011 | target 2012 |
Solar project X4-017, Wicomico County Solar |
20.0 MW | Withdrawn / abandoned |
Wicomico, MD | PJM |
Nov 2011 | target 2017 |
Solar project W4-078, Dorchester County Solar |
20.0 MW | Withdrawn / abandoned |
Dorchester, MD | PJM |
Jan 2011 | target 2013 |
Solar project X2-084, Dorchester County Solar |
19.6 MW | Withdrawn / abandoned |
Dorchester, MD | PJM |
Jul 2011 | target 2012 |
Linkwood Solar Solar |
19.5 MW | Withdrawn / abandoned |
Dorchester, MD | PJM |
Aug 2011 | target 2017 |
Solar project X3-074, Kent County Solar |
11.9 MW | Withdrawn / abandoned |
Kent, MD | PJM |
Oct 2011 | target 2013 |
Solar project X1-025, St. Mary's County Solar |
10.0 MW | Withdrawn / abandoned |
St. Mary's, MD | PJM |
Feb 2011 | target 2012 |
Solar project X1-022, St. Mary's County Solar |
10.0 MW | Withdrawn / abandoned |
St. Mary's, MD | PJM |
Feb 2011 | target 2012 |
Solar project W4-076, Prince George's County Solar |
10.0 MW | Withdrawn / abandoned |
Prince George's, MD | PJM |
Jan 2011 | target 2011 |
Solar project W4-096, Wicomico County Solar |
10.0 MW | Withdrawn / abandoned |
Wicomico, MD | PJM |
Jan 2011 | target 2013 |
Solar project X3-073, Kent County Solar |
9.8 MW | Withdrawn / abandoned |
Kent, MD | PJM |
Oct 2011 | target 2013 |
Solar project X1-023, St. Mary's County Solar |
6.0 MW | Withdrawn / abandoned |
St. Mary's, MD | PJM |
Feb 2011 | target 2012 |
Washington County Renewable Energy Project Other |
2.0 MW | Withdrawn / abandoned |
Washington, MD | PJM |
Jun 2011 | target 2013 |
Solar project X3-067, Queen Anne's County Solar |
2.0 MW | Withdrawn / abandoned |
Queen Anne's, MD | PJM |
Oct 2011 | target 2012 |