United States β€Ί Grid β€Ί Interconnection queues β€Ί Maryland

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Maryland (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3124 MW
Active in queue49.0 MW1 requests
Agreement signed0.0 MW0 requests
Withdrawn23616 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Wildcat Point
Gas
90.0 MWOperating Cecil, MDPJM Mar 20182017
Calvert Cliffs Units 1 and 2 (f/k/a PJM Queue M04)
Nuclear
28.1 MWOperating Calvert, MDPJM Apr 20182023
Spectrum Solar
Solar
5.6 MWOperating Prince George's, MDPJM Feb 20182024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)