United States β€Ί Grid β€Ί Interconnection queues β€Ί Maine

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Maine (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown10390 MW
Active in queue144 MW4 requests
Agreement signed144 MW4 requests
Withdrawn20289 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Cross Town Battery Storage
Battery storage
175 MWOperating Cumberland, MEISO-NE Apr 2019target 2025
Millinocket Battery additon
Other
126 MWOperating Penobscot, MEISO-NE Apr 2019target 2020
Mousam River Solar
Solar
20.0 MWOperating York, MEISO-NE Aug 2019target 2025
Solar
Solar
20.0 MWOperating Androscoggin, MEISO-NE Sep 2019target 2024
Milo Solar
Solar
20.0 MWOperating Piscataquis, MEISO-NE Mar 2019target 2021
ND OTM LLC Generator Reactivation
Other
8.0 MWOperating Penobscot, MEISO-NE Dec 2019target 2021
Solar
Solar
7.2 MWOperating Kennebec, MEISO-NE Aug 2019target 2021
Solar
Solar
4.8 MWOperating York, MEISO-NE Aug 2019target 2022
Solar
Solar
4.6 MWOperating Oxford, MEISO-NE Aug 2019target 2021
Solar
Solar
4.6 MWOperating Oxford, MEISO-NE Aug 2019target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)