πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Louisiana

OCTARY USA Β· INTERCONNECTION QUEUES

Onshore wind interconnection queue in Louisiana

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3536 MW
Active in queue536 MW3 requests
Agreement signed0.0 MW0 requests
Withdrawn61,042 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J3368, St. Landry Parish County
Onshore wind
200 MWIn study St. Landry Parish, LAMISO Apr 2024target 2028
Onshore wind project J2965, Morehouse Parish County
Onshore wind
180 MWIn study Morehouse Parish, LAMISO Sep 2022target 2025
Onshore wind project J3394, St. Landry Parish County
Onshore wind
156 MWIn study St. Landry Parish, LAMISO Apr 2024target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)