Completed queue projects in Kansas (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown71,715 MW
Active in queue322 MW2 requests
Agreement signed322 MW2 requests
Withdrawn193,440 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2016-174, Nemaha County
Onshore wind
302 MWOperating Nemaha, KSSPP Nov 20162020
Onshore wind project GEN-2016-176, Nemaha County
Onshore wind
302 MWOperating Nemaha, KSSPP Dec 20162021
Onshore wind project GEN-2016-149, Washington County
Onshore wind
302 MWOperating Washington, KSSPP Nov 20162023
Onshore wind project GEN-2016-150, Nemaha County
Onshore wind
302 MWOperating Nemaha, KSSPP Nov 20162023
Onshore wind project GEN-2016-046, Ford County
Onshore wind
299 MWOperating Ford, KSSPP Mar 20162021
Onshore wind project GEN-2016-153, Harper County
Onshore wind
134 MWOperating Harper, KSSPP Nov 20162025
Onshore wind project GEN-2016-067, Thomas County
Onshore wind
73.6 MWOperating Thomas, KSSPP Mar 20162019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)