πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Iowa (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2425 MW
Active in queue1,064 MW11 requests
Agreement signed599 MW7 requests
Withdrawn81,195 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J1050, Boone County
Onshore wind
225 MWOperating Boone, IAMISO Mar 20182022
Onshore wind project J1181, Chickasaw County
Onshore wind
200 MWOperating Chickasaw, IAMISO Mar 20182022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)