Queue projects under construction in Iowa

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7950 MW
Active in queue23.9 GW123 requests
Agreement signed1,860 MW18 requests
Withdrawn29566.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J877, Palo Alto County
Solar
250 MWUnder construction Palo Alto, IAMISO Jun 2017target 2023
Solar project J1174, Worth County
Solar
165 MWUnder construction Worth, IAMISO Mar 2018target 2024
Solar project J1084, Clinton County
Solar
150 MWUnder construction Clinton, IAMISO Mar 2018target 2023
Solar project J1520, Worth County
Solar
135 MWUnder construction Worth, IAMISO Jun 2020target 2027
Solar project J1131, Scott County
Solar
100 MWUnder construction Scott, IAMISO Mar 2018target 2024
Onshore wind project J898, Howard County
Onshore wind
100 MWUnder construction Howard, IAMISO Jun 2017target 2023
Solar project J1132, Union County
Solar
50.0 MWUnder construction Union, IAMISO Mar 20182024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)