United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

OCTARY USA Β· INTERCONNECTION QUEUES

Queue requests in study in Indiana (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6633 MW
Active in queue6,266 MW47 requests
Agreement signed5,333 MW38 requests
Withdrawn376,324 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Vermilion Grove Wind
Onshore wind Β· Vermilion Grove Wind, LLC
255 MWIn study Vermillion, INPJM Sep 2019target 2022
Bowfin Solar
Solar + storage
150 MWPaused / redesign Huntington, INPJM Aug 2019target 2028
Riverstart Solar Park V
Solar
100 MWPaused / redesign Randolph, INPJM Mar 2019target 2026
Dover Solar Facility
Solar
55.0 MWPaused / redesign Whitley, INPJM Mar 2019target 2026
Golden Aster Solar Energy Center
Battery storage
40.0 MWPaused / redesign Grant, INPJM Mar 2019target 2026
Meadow Forge Solar Energy Center
Solar
33.0 MWPaused / redesign Delaware, INPJM Mar 2019target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)