United States β€Ί Grid β€Ί Interconnection queues β€Ί Illinois

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Illinois (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown41,532 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn163,125 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Three Rivers Energy Center
Gas
1,160 MWOperating Grundy, ILPJM Oct 20152023
Onshore wind project J468, Douglas County
Onshore wind
202 MWOperating Douglas, ILMISO Jun 20152019
Onshore wind project J456, Mcdonough County
Onshore wind
150 MWOperating Mcdonough, ILMISO May 20152019
Marengo Battery Storage
Battery storage
20.0 MWOperating Mchenry, ILPJM Apr 20152018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)