United States β€Ί Grid β€Ί Interconnection queues β€Ί Idaho

OCTARY USA Β· INTERCONNECTION QUEUES

Gas interconnection queue in Idaho

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown81,861 MW
Active in queue1,861 MW8 requests
Agreement signed0.0 MW0 requests
Withdrawn7722.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 760, Elmore County
Gas
526 MWIn study Elmore, IDWest Apr 2025target 2030
Gas project 759, Elmore County
Gas
526 MWIn study Elmore, IDWest Apr 2025target 2030
Gas project T2-040, Power County
Gas
400 MWIn study Power, IDWest Sep 2025target 2031
Gas project 758, Elmore County
Gas
167 MWIn study Elmore, IDWest Mar 2025target 2028
Gas project CS25-05, Kootenai County
Gas
102 MWIn study Kootenai, IDWest Apr 2025target 2029
Gas project CS25-04, Kootenai County
Gas
102 MWIn study Kootenai, IDWest Apr 2025target 2027
Gas project 796, Elmore County
Gas
19.3 MWIn study Elmore, IDWest Sep 2025target 2031
Gas project 797, Twin Falls County
Gas
19.3 MWIn study Twin Falls, IDWest Sep 2025target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)