United States β€Ί Grid β€Ί Interconnection queues β€Ί Idaho

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Idaho (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown113,057 MW
Active in queue455 MW2 requests
Agreement signed455 MW2 requests
Withdrawn113,057 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

11 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Wind + storage project 587, Jerome County
Wind + storage Β· Magic Valley Energy, LLC
1,050 MWWithdrawn / abandoned Jerome, IDWest Aug 2020target 2023
Other project 591, Elmore County
Other
400 MWWithdrawn / abandoned Elmore, IDWest Dec 2020
Solar + storage project 1212, Bear Lake County
Solar + storage
350 MWWithdrawn / abandoned Bear Lake, IDWest Apr 2020target 2023
Solar + storage project 1199, Power County
Solar + storage
300 MWWithdrawn / abandoned Power, IDWest Mar 2020target 2023
Other project 580, Bingham County
Other Β· Arco Wind, LLC
263 MWWithdrawn / abandoned Bingham, IDWest May 2020target 2020
Gas project TCS-13, Kootenai County
Gas
200 MWWithdrawn / abandoned Kootenai, IDWest Nov 2020target 2026
Gas project 109, Kootenai County
Gas
200 MWWithdrawn / abandoned Kootenai, IDWest Nov 2020target 2026
Solar + storage project 1201, Clark County
Solar + storage
200 MWWithdrawn / abandoned Clark, IDWest Mar 2020target 2023
Other project 578, Elmore County
Other
87.0 MWWithdrawn / abandoned Elmore, IDWest Feb 2020
Other project 577, Ada County
Other
6.4 MWWithdrawn / abandoned Ada, IDWest Jan 2020
Solar project 1233, Bannock County
Solar
0.1 MWWithdrawn / abandoned Bannock, IDWest Aug 2020target 2020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)