Completed queue projects in Idaho

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2203,999 MW
Active in queue21.0 GW83 requests
Agreement signed4,070 MW23 requests
Withdrawn55888.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

220 requests · page 1 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 239, Payette County
Gas
345 MWOperating Payette, IDWest Apr 20082012
Gas project 270, Elmore County
Gas
210 MWOperating Elmore, IDWest Oct 2008
Gas project 88, Elmore County
Gas
200 MWOperating Elmore, IDWest Apr 2003target 2008
Solar project 567, Ada County
Solar · Pleasant Valley Solar, LLC
200 MWOperating Ada, IDWest Sep 20192025
Gas project 97, Elmore County
Gas
162 MWOperating Elmore, IDWest Oct 2003target 2005
Onshore wind project 255, Bingham County
Onshore wind · Cedar Creek Wind, LLC
152 MWOperating Bingham, IDWest Dec 2008target 2023
Battery storage project 657, Ada County
Battery storage · Kuna BESS LLC
150 MWOperating Ada, IDWest May 20222025
Onshore wind project 29-B, Bonneville County
Onshore wind · Wolverine Creek Goshen Interconnection, LLC
125 MWOperating Bonneville, IDWest Sep 2003target 2010
Onshore wind project 341, Bonneville County
Onshore wind · Meadow Creek Project Company, LLC
120 MWOperating Bonneville, IDWest Jun 2010target 2012
Hydro project 795, Power County
Hydro · Idaho Power Company - Power Supply
118 MWOperating Power, IDWest Jul 2025
Onshore wind project 117, Twin Falls County
Onshore wind
102 MWOperating Twin Falls, IDWest Jan 20052010
Solar + storage project 549, Twin Falls County
Solar + storage · Franklin Solar LLC
100 MWOperating Twin Falls, IDWest Mar 20192024
Hydro project 237, Ada County
Hydro
100 MWOperating Ada, IDWest Oct 2007target 2008
Other project 2, Elmore County
Other
90.0 MWOperating Elmore, IDWest Feb 2001target 2001
Battery storage project 629, Owyhee County
Battery storage · Idaho Power Company‚ÄîPower Supply
85.0 MWOperating Owyhee, IDWest Dec 20212025
Onshore wind project 293, Power County
Onshore wind
80.0 MWOperating Power, IDWest Jun 20092011
Battery storage project 619, Owyhee County
Battery storage · Idaho Power Company‚ÄîPower Supply
80.0 MWOperating Owyhee, IDWest Oct 20212023
Battery storage project 638, Canyon County
Battery storage · Idaho Power Company‚ÄîPower Supply
80.0 MWOperating Canyon, IDWest Feb 2022target 2025
Onshore wind project 29-A, Bonneville County
Onshore wind · Wolverine Creek Goshen Interconnection, LLC
64.5 MWOperating Bonneville, IDWest Sep 2003target 2006
Hydro project 136, Twin Falls County
Hydro
64.0 MWOperating Twin Falls, IDWest Jun 20052017
Other project 753, Twin Falls County
Other · Idaho Power Company-Power Supply
59.0 MWOperating Twin Falls, IDWest Jan 2025
Horse Butte Wind
Onshore wind · Horse Butte Wind I LLC
57.6 MWOperating Bonneville, IDWest Jun 2009target 2010
Onshore wind project 334, Twin Falls County
Onshore wind
40.0 MWOperating Twin Falls, IDWest Jun 20102012
Solar + storage project 557, Elmore County
Solar + storage · Black Mesa Interconnection, LLC
40.0 MWOperating Elmore, IDWest Apr 20192023
Solar project 432, Ada County
Solar
40.0 MWOperating Ada, IDWest Jul 2014
Smith Creek
Hydro
39.0 MWOperating Boundary, IDWest Jul 2015target 1987
Onshore wind project 317, Elmore County
Onshore wind
22.0 MWOperating Elmore, IDWest Feb 20102011
Onshore wind project 323-A, Power County
Onshore wind · Power County Wind Park North, LLC
21.6 MWOperating Power, IDWest Mar 2010target 2011
Onshore wind project 323-B, Power County
Onshore wind · Power County Wind Park South, LLC
21.6 MWOperating Power, IDWest Mar 2010target 2011
Onshore wind project 357, Twin Falls County
Onshore wind
21.0 MWOperating Twin Falls, IDWest Oct 20102011
Onshore wind project 159, Twin Falls County
Onshore wind
21.0 MWOperating Twin Falls, IDWest Dec 20052011
Gas project 610, Payette County
Gas · Idaho Power Company‚ÄîPower Supply
20.0 MWOperating Payette, IDWest Jun 20212022
Solar project 441, Elmore County
Solar
20.0 MWOperating Elmore, IDWest Oct 2014target 2016
Solar project 394, Elmore County
Solar
20.0 MWOperating Elmore, IDWest Mar 2012target 2016
Solar project 428, Elmore County
Solar
20.0 MWOperating Elmore, IDWest Jun 2014target 2016
Onshore wind project 339, Elmore County
Onshore wind
20.0 MWOperating Elmore, IDWest Jun 20102012
Solar project 426, Owyhee County
Solar
20.0 MWOperating Owyhee, IDWest Jun 2014target 2016
Solar project 431, Power County
Solar
20.0 MWOperating Power, IDWest Jul 2014target 2016
Solar project 435, Elmore County
Solar
20.0 MWOperating Elmore, IDWest Oct 2014target 2016
Solar project 433, Power County
Solar
20.0 MWOperating Power, IDWest Jul 2014target 2016
Solar project 523, Twin Falls County
Solar · Jackpot Holdings, LLC
20.0 MWOperating Twin Falls, IDWest May 20172022
Onshore wind project 338, Elmore County
Onshore wind
20.0 MWOperating Elmore, IDWest Jun 20102012
Onshore wind project 336, Elmore County
Onshore wind
20.0 MWOperating Elmore, IDWest Jun 20102012
Solar project 395, Elmore County
Solar
20.0 MWOperating Elmore, IDWest Mar 2012target 2016
Onshore wind project 340, Elmore County
Onshore wind
20.0 MWOperating Elmore, IDWest Jun 20102012
Solar project 517, Twin Falls County
Solar · Jackpot Holdings, LLC
20.0 MWOperating Twin Falls, IDWest Jul 20162022
Solar project 503, Twin Falls County
Solar · Jackpot Holdings, LLC
20.0 MWOperating Twin Falls, IDWest Aug 20152022
Solar project 502, Twin Falls County
Solar · Jackpot Holdings, LLC
20.0 MWOperating Twin Falls, IDWest Aug 20152022
Solar project 397, Elmore County
Solar
20.0 MWOperating Elmore, IDWest Jun 2012target 2016
Solar project 513, Twin Falls County
Solar · Jackpot Holdings, LLC
20.0 MWOperating Twin Falls, IDWest Mar 20162022
Page 1 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)