United States β€Ί Grid β€Ί Interconnection queues β€Ί Georgia

OCTARY USA Β· INTERCONNECTION QUEUES

Queue requests in study in Georgia (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown61,090 MW
Active in queue1,883 MW12 requests
Agreement signed708 MW5 requests
Withdrawn274,760 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project IC-932, Glynn County
Solar + storage
250 MWPaused / redesign Glynn, GASoutheast Dec 2020target 2024
Solar + storage project IC-933, Glynn County
Solar + storage
250 MWPaused / redesign Glynn, GASoutheast Dec 2020target 2024
Solar project IC-908, Turner County
Solar
220 MWPaused / redesign Turner, GASoutheast Oct 2020target 2023
Cherry Blossom Solar
Solar + storage
150 MWIn study Twiggs, GASoutheast Aug 20202023
Moxley Solar
Solar
120 MWIn study Jefferson, GASoutheast Nov 2020target 2024
RV Solar
Solar
100 MWIn study Tattnall, GASoutheast Feb 20202022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)