Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown22,600 MW
Active in queue2,600 MW2 requests
Agreement signed0.0 MW0 requests
Withdrawn74,780 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Nuclear project 107, Miami-Dade County
Nuclear Β· FPL
1,300 MWIn study Miami-Dade, FLSoutheast Aug 2007target 2027
Nuclear project 108, Miami-Dade County
Nuclear Β· FPL
1,300 MWIn study Miami-Dade, FLSoutheast Aug 2007target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)