United States β€Ί Grid β€Ί Interconnection queues β€Ί Florida

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Florida (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown13921 MW
Active in queue1,593 MW22 requests
Agreement signed103 MW2 requests
Withdrawn13921 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

13 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 380E, Jackson County
Solar Β· Third Party
80.0 MWWithdrawn / abandoned Jackson, FLSoutheast Mar 2020target 2024
Solar project 276, Alachua County
Solar Β· Masked
74.9 MWWithdrawn / abandoned Alachua, FLSoutheast Feb 2020target 2022
Solar project 278, Alachua County
Solar Β· Origis Holdings USA Subco, LLC
74.9 MWWithdrawn / abandoned Alachua, FLSoutheast Mar 2020target 2022
Solar project 289, Alachua County
Solar Β· Masked
74.9 MWWithdrawn / abandoned Alachua, FLSoutheast Oct 2020target 2023
Solar project 275, Polk County
Solar Β· Masked
74.9 MWWithdrawn / abandoned Polk, FLSoutheast Feb 2020target 2022
Solar project 69, Polk County
Solar
74.5 MWWithdrawn / abandoned Polk, FLSoutheast Apr 2020target 2023
Solar project 68, Polk County
Solar
74.5 MWWithdrawn / abandoned Polk, FLSoutheast Apr 2020target 2023
Solar project 73, Polk County
Solar
74.5 MWWithdrawn / abandoned Polk, FLSoutheast Apr 2020target 2023
Solar project 287, Manatee County
Solar Β· Masked
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast Jun 2020target 2022
Solar project 74, Polk County
Solar
74.5 MWWithdrawn / abandoned Polk, FLSoutheast Apr 2020target 2023
Solar project 280, Osceola County
Solar Β· Masked
74.3 MWWithdrawn / abandoned Osceola, FLSoutheast Mar 2020target 2023
Solar project 279, Osceola County
Solar Β· Hamel Renewables, LLC
74.3 MWWithdrawn / abandoned Osceola, FLSoutheast Mar 2020target 2023
Solar project 380D, Calhoun County
Solar Β· Third Party
20.0 MWWithdrawn / abandoned Calhoun, FLSoutheast Feb 2020target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)