United States β€Ί Grid β€Ί Interconnection queues β€Ί Florida

OCTARY USA Β· INTERCONNECTION QUEUES

Queue projects under construction in Florida (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6581 MW
Active in queue7,352 MW95 requests
Agreement signed0.0 MW0 requests
Withdrawn523,820 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 328, Pinellas County
Gas Β· Duke Energy Florida, LLC
172 MWUnder construction Pinellas, FLSoutheast Jun 2023target 2024
Battery storage project 327, Citrus County
Battery storage Β· Duke Energy Florida, LLC
100 MWUnder construction Citrus, FLSoutheast May 2023target 2027
Gas project 333, Polk County
Gas Β· Duke Energy Florida, LLC
84.0 MWUnder construction Polk, FLSoutheast Jul 2023target 2025
Solar project 326, Osceola County
Solar Β· Duke Energy Florida, LLC
74.9 MWUnder construction Osceola, FLSoutheast May 2023target 2027
Solar project 323, Jackson County
Solar Β· Duke Energy Florida, LLC
74.9 MWUnder construction Jackson, FLSoutheast Feb 2023target 2027
Solar project 325, Osceola County
Solar Β· Duke Energy Florida, LLC
74.9 MWUnder construction Osceola, FLSoutheast May 2023target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)