Withdrawn queue requests in Delaware (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown111,786 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn111,786 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

11 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Offshore wind project AG1-087, Sussex County
Offshore wind
440 MWWithdrawn / abandoned Sussex, DEPJM Jul 2020target 2026
Offshore wind project AF2-193, Sussex County
Offshore wind Β· GSOE I, LLC
440 MWWithdrawn / abandoned Sussex, DEPJM Mar 2020target 2026
Offshore wind project AF2-194, Sussex County
Offshore wind Β· GSOE I, LLC
440 MWWithdrawn / abandoned Sussex, DEPJM Mar 2020target 2026
Solar + storage project AG1-497, Kent County
Solar + storage Β· Morgan Branch Solar I, LLC
120 MWWithdrawn / abandoned Kent, DEPJM Sep 2020target 2023
Solar project AG1-061, Sussex County
Solar Β· Deere Acres Solar LLC
109 MWWithdrawn / abandoned Sussex, DEPJM Jul 2020target 2021
Solar project AF2-385, Sussex County
Solar
75.0 MWWithdrawn / abandoned Sussex, DEPJM Mar 2020target 2022
Battery storage project AF2-207, Sussex County
Battery storage
50.4 MWWithdrawn / abandoned Sussex, DEPJM Mar 2020target 2022
Battery storage project AG1-464, Kent County
Battery storage
50.0 MWWithdrawn / abandoned Kent, DEPJM Sep 2020target 2023
Solar project AG1-461, Sussex County
Solar
30.0 MWWithdrawn / abandoned Sussex, DEPJM Sep 2020target 2023
Offshore wind project AF2-196, Sussex County
Offshore wind
30.0 MWWithdrawn / abandoned Sussex, DEPJM Mar 2020target 2022
TES Blue Hen Solar 23
Solar
1.5 MWWithdrawn / abandoned Kent, DEPJM Jul 2020target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)