Requests shown329.9 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn91,307 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Red Lion Energy Center
Other
24.9 MWOperating New Castle, DEPJM Apr 20112012
Brookside Energy Center
Other
3.0 MWOperating New Castle, DEPJM Jul 20112012
PBF Delaware City Refinery Units G3, G6 & G7
Gas
2.0 MWOperating New Castle, DEPJM Oct 20112013

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)