United States β€Ί Grid β€Ί Interconnection queues β€Ί Connecticut

OCTARY USA Β· INTERCONNECTION QUEUES

Queue requests in study in Connecticut

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown230.0 MW
Active in queue678 MW7 requests
Agreement signed648 MW5 requests
Withdrawn17129.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar
Solar
25.0 MWIn study Hartford, CTISO-NE Apr 2022target 2027
Solar Increase
Solar
5.0 MWIn study Hartford, CTISO-NE Feb 2023target 2027

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20222023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)