United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Colorado (2010 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4302 MW
Active in queue302 MW4 requests
Agreement signed302 MW4 requests
Withdrawn182,484 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GI-2010-19, Pueblo County
Solar
120 MWAgreement signed Pueblo, COWest Nov 20102016
Coal project GI-2010-8, Pueblo County
Coal
100 MWAgreement signed Pueblo, COWest May 2010target 2010
Solar project GI-2010-11, Alamosa County
Solar
52.0 MWAgreement signed Alamosa, COWest Jul 2010target 2016
Solar project GI-2010-4, Alamosa County
Solar
30.0 MWAgreement signed Alamosa, COWest Feb 2010target 2012

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)