Withdrawn queue requests in Colorado (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5813.3 GW
Active in queue340 MW4 requests
Agreement signed260 MW3 requests
Withdrawn5813.3 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

58 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-2017-47, Kiowa County
Onshore wind
1,000 MWWithdrawn / abandoned Kiowa, COWest Nov 2017target 2020
Onshore wind project GI-2017-24, Morgan County
Onshore wind
630 MWWithdrawn / abandoned Morgan, COWest Jul 2017target 2020
Onshore wind project GI-2017-20, Kiowa County
Onshore wind
600 MWWithdrawn / abandoned Kiowa, COWest Jun 2017target 2020
Solar project GI-2017-38, Arapahoe County
Solar
575 MWWithdrawn / abandoned Arapahoe, COWest Sep 2017target 2023
Solar project GI-2017-37, Pueblo County
Solar
575 MWWithdrawn / abandoned Pueblo, COWest Sep 2017target 2023
Solar project GI-2017-49, Pueblo County
Solar
500 MWWithdrawn / abandoned Pueblo, COWest Nov 2017target 2022
Solar project GI-2017-46, Huerfano County
Solar
500 MWWithdrawn / abandoned Huerfano, COWest Nov 2017target 2020
Solar project GI-2017-11, Lincoln County
Solar
500 MWWithdrawn / abandoned Lincoln, COWest Mar 2017target 2020
Onshore wind project GI-2017-26, Bent County
Onshore wind
500 MWWithdrawn / abandoned Bent, COWest Aug 2017target 2020
Onshore wind project GI-2017-44, Huerfano County
Onshore wind
400 MWWithdrawn / abandoned Huerfano, COWest Nov 2017target 2020
Solar project GI-2017-13, Arapahoe County
Solar
400 MWWithdrawn / abandoned Arapahoe, COWest Apr 2017target 2020
Onshore wind project GI-2017-43, Huerfano County
Onshore wind
400 MWWithdrawn / abandoned Huerfano, COWest Nov 2017target 2020
Solar project GI-2017-35, Pueblo County
Solar
400 MWWithdrawn / abandoned Pueblo, COWest Sep 2017target 2020
Onshore wind project GI-2017-29, Pueblo County
Onshore wind
350 MWWithdrawn / abandoned Pueblo, COWest Aug 2017target 2020
Onshore wind project GI-2017-41, Kit Carson County
Onshore wind
302 MWWithdrawn / abandoned Kit Carson, COWest Nov 2017target 2020
Onshore wind project GI-2017-40, Prowers County
Onshore wind
302 MWWithdrawn / abandoned Prowers, COWest Nov 2017target 2020
Solar project GI-2017-31, Pueblo County
Solar
300 MWWithdrawn / abandoned Pueblo, COWest Aug 2017target 2019
Solar project GI-2017-33, Pueblo County
Solar
300 MWWithdrawn / abandoned Pueblo, COWest Sep 2017target 2019
Onshore wind project GI-2017-17, Elbert County
Onshore wind
300 MWWithdrawn / abandoned Elbert, COWest Jun 2017target 2020
Solar project GI-2017-30, Pueblo County
Solar
300 MWWithdrawn / abandoned Pueblo, COWest Aug 2017target 2020
Solar project GI-2017-19, Arapahoe County
Solar
250 MWWithdrawn / abandoned Arapahoe, COWest Jun 2017target 2020
Solar project GI-2017-50, Lincoln County
Solar
250 MWWithdrawn / abandoned Lincoln, COWest Nov 2017target 2022
Onshore wind project GI-2017-23, Lincoln County
Onshore wind
201 MWWithdrawn / abandoned Lincoln, COWest Jul 2017target 2018
Onshore wind project GI-2017-14, Lincoln County
Onshore wind
201 MWWithdrawn / abandoned Lincoln, COWest May 2017target 2018
Onshore wind project GI-2017-45, Huerfano County
Onshore wind
200 MWWithdrawn / abandoned Huerfano, COWest Nov 2017target 2020
Onshore wind project GEN-2017-032, Kiowa County
Onshore wind
200 MWWithdrawn / abandoned Kiowa, COSPP May 20172023
Solar project GI-2017-27, Pueblo County
Solar
200 MWWithdrawn / abandoned Pueblo, COWest Aug 2017target 2019
Solar project GI-2017-34, Pueblo County
Solar
200 MWWithdrawn / abandoned Pueblo, COWest Sep 2017target 2020
Onshore wind project GI-2017-42, Kiowa County
Onshore wind
200 MWWithdrawn / abandoned Kiowa, COWest Nov 2017target 2020
Solar project GI-2017-25, Pueblo County
Solar
150 MWWithdrawn / abandoned Pueblo, COWest Aug 2017target 2019
Solar project GI-2017-36, Adams County
Solar
150 MWWithdrawn / abandoned Adams, COWest Sep 2017target 2020
Solar project GI-2017-39, Pueblo County
Solar
150 MWWithdrawn / abandoned Pueblo, COWest Oct 2017target 2019
Solar project GI-2017-16, El Paso County
Solar
150 MWWithdrawn / abandoned El Paso, COWest Jun 2017target 2020
Solar project GI-2017-2, Arapahoe County
Solar
150 MWWithdrawn / abandoned Arapahoe, COWest Jan 2017target 2019
Solar project GI-2017-10, Arapahoe County
Solar
150 MWWithdrawn / abandoned Arapahoe, COWest Feb 2017target 2019
Solar project GI-2017-18, Morgan County
Solar
120 MWWithdrawn / abandoned Morgan, COWest Jun 2017target 2020
Solar project GI-2017-3, Pueblo County
Solar
100 MWWithdrawn / abandoned Pueblo, COWest Jan 2017target 2019
Solar project GI-2017-32, Lincoln County
Solar
100 MWWithdrawn / abandoned Lincoln, COWest Sep 2017target 2021
Onshore wind project 17-08212, Larimer County
Onshore wind
100 MWWithdrawn / abandoned Larimer, COWest Aug 2017target 2020
Solar + storage project GI-2017-28, Pueblo County
Solar + storage
100 MWWithdrawn / abandoned Pueblo, COWest Aug 2017target 2019
Onshore wind project 17-08211, Larimer County
Onshore wind
100 MWWithdrawn / abandoned Larimer, COWest Aug 2017target 2020
Solar project GI-2017-9, Pueblo County
Solar
80.0 MWWithdrawn / abandoned Pueblo, COWest Feb 2017target 2019
Onshore wind project 17-08072, Larimer County
Onshore wind
80.0 MWWithdrawn / abandoned Larimer, COWest Aug 2017target 2019
Solar project GI-2017-48, Weld County
Solar
75.0 MWWithdrawn / abandoned Weld, COWest Nov 2017target 2020
Solar project GI-2017-51, Arapahoe County
Solar
75.0 MWWithdrawn / abandoned Arapahoe, COWest Dec 2017target 2020
Solar project BHCT G22, Pueblo County
Solar
60.0 MWWithdrawn / abandoned Pueblo, COWest May 2017target 2020
Solar project GI-2017-8, Park County
Solar
50.0 MWWithdrawn / abandoned Park, COWest Feb 2017target 2019
Solar project GI-2017-6, Adams County
Solar
50.0 MWWithdrawn / abandoned Adams, COWest Feb 2017target 2019
Solar project GI-2017-4, Delta County
Solar
50.0 MWWithdrawn / abandoned Delta, COWest Jan 2017target 2019
Solar project GI-2017-7, Weld County
Solar
50.0 MWWithdrawn / abandoned Weld, COWest Feb 2017target 2019
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)