OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Colorado (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4657 MW
Active in queue60.0 MW1 requests
Agreement signed0.0 MW0 requests
Withdrawn4657 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2015-012, Lincoln County
Onshore wind
300 MWWithdrawn / abandoned Lincoln, COSPP Mar 2015target 2017
Onshore wind project GI-2015-1, Elbert County
Onshore wind
250 MWWithdrawn / abandoned Elbert, COWest May 2015target 2016
Solar project BHCT G20, Pueblo County
Solar Β· Black Hills Electric Generation LLC
60.0 MWWithdrawn / abandoned Pueblo, COWest Nov 2015target 2022
Solar project BHCT G17, Pueblo County
Solar
46.4 MWWithdrawn / abandoned Pueblo, COWest Jan 2015target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)