United States β€Ί Grid β€Ί Interconnection queues β€Ί California

OCTARY USA Β· INTERCONNECTION QUEUES

Geothermal interconnection queue in California

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5450 MW
Active in queue450 MW5 requests
Agreement signed0.0 MW0 requests
Withdrawn181,520 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Geothermal project GI-2023-174, Imperial County
Geothermal
157 MWIn study Imperial, CAWest Apr 2023target 2029
Geothermal project GI-2023-176, Imperial County
Geothermal
157 MWIn study Imperial, CAWest Apr 2023target 2029
Mayacamas Geothermal
Geothermal
53.0 MWIn study Sonoma, CACAISO Apr 2021target 2030
Geothermal project GI-2020-130, Imperial County
Geothermal
50.0 MWIn study Imperial, CAWest Jan 2020target 2028
Geothermal project GI-2023-177, Imperial County
Geothermal
33.0 MWIn study Imperial, CAWest Apr 2023target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)