United States βΊ Grid βΊ Interconnection queues βΊ Arkansas
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Arkansas (2016 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project J696, St. Francis County Solar |
150 MW | Withdrawn / abandoned |
| Solar project J655, Jackson County Solar |
102 MW | Withdrawn / abandoned |
| Solar project J656, Craighead County Solar |
102 MW | Withdrawn / abandoned |
| Solar project J654, Arkansas County Solar |
102 MW | Withdrawn / abandoned |
| Onshore wind project J662, Crittenden County Onshore wind |
100 MW | Withdrawn / abandoned |
| Solar project J622, Lonoke County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J681, Jackson County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J621, Lincoln County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J677, Cross County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J666, Crittenden County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J684, Pulaski County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J678, St. Francis County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J617, Lincoln County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J695, Prairie County Solar |
99.0 MW | Withdrawn / abandoned |
| Solar project J688, Clark County Solar |
92.0 MW | Withdrawn / abandoned |
| Solar project J661, Bradley County Solar |
90.0 MW | Withdrawn / abandoned |
| Solar project J689, Cross County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project J653, White County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project J690, Lonoke County Solar |
42.0 MW | Withdrawn / abandoned |
| Solar project GEN-2016-166, Washington County Solar |
35.0 MW | Withdrawn / abandoned |
| Other project J685, Clark County Other |
30.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)